JXSC has provided a successful 10 TPH alluvial tin process plant in Tanzania. We design the separation process plant flowchart & plant layout drawing according to mineral ore's conditions and offer a complete set of plant machines.

10 TPH Alluvial Tin Process Plant Project Case

Introduction

Minerals: Alluvial tin(without stickly clay)
Capacity:10 TPH
Process:Feeding -> Washing & Screening -> Gravity Separation

Solutions & Process

Alluvial Tungsten & Tin Gravity Separation Plant Flowchart

IMG_256

This setup is a 10 tons per hour alluvial tungsten/tin processing plant.It is configured with a vibrating feeder, trommel screen, jig concentrators, shaker tables, belt conveyors, etc. The process is as below:

·The raw ore will be fed into the raw ore hopper abovevibrating feederby the excavator. The vibrating feeder is designed with a grizzly bar, and bar gap of 75mm, which can feed smaller than 75mm into a Trommel screen.

·The less than 70mm goes totrommel screenfor washing and screening. Later we can get 3 kinds of outputs: less than 2mm, 2-15mm, and larger than 15mm(waste stone).

·After washing by the trommel screen, 2-15mm will go to one set of rough jig concentratorsfor 1st coarse tin separation, then we can get 2-15mm tin rough concentrate.

·The less than 2mm goes to another rough jig concentrator for enrichment, and then the concentrate goes to the shaker table for further separation.

·Aftershaker table, we can get 0-2mm tin rough concentrate.